1. On receipt of the lifeboat, all items of loose equipment should be checked against the boat packing/loose equipment sheet.
2. Loose equipment supplied with the boat should be stowed in the forward locker and in the brackets and fixing positions provided.
3. Any additional items of equipment required to fulfil the Authority Regulation should be obtained and stowed.
4. Ensure that the fuel taps at engine and fuel tank are open.
5. Check fuel tank, engine and gearbox lubricant and coolant levels. Top up as necessary.
6. Put lifeboat into the water and check the operation of the hook release gear. Refer to hook release gear data. Check also for general boat water tightness.
7. Start engine following instruction labels attached to the helmsman’s console.
8. Check that the oil pressure, water temperature and electric charging warning lights are not alight.
9. Give boat a short trial to ensure that the engine, gearbox and steering function correctly, and that there are no leaks through hull fittings.
10.Whilst the engine is running, a check should be made to ensure that the oil pressure, water temperature and alternator charging lights remain off. Also check fuel, cooling and lubricating oil systems for leakage.
11.On completing of running trials:
(a) Having stopped the engine, return the stop control to the “run” position.
(b) Top up fuel tank, check coolant and lubricating oil levels.
(c) Check that battery is fully charged.
(d) Drain water using the bilge pump.
12. Ensure that the shackles on the slings are correctly secured into the lifting foundations. Attach the slings to the davit fall wires. Lift boat and stow in davit in accordance with the davit Instruction/Maintenance manual. These instructions should be rigidly adhered to.
13. Install craft onto ramp and engage the main securing link into the aft deck release hook. This is done by operating the hook using the hydraulic hook release device. When the hook is closed, turn the switch of manual-operated pump clockwise until it can not move.
14. Ensure the gunwale boat chock engage correctly on the davit.
15. Carry out boat installation and davit tests as required by the appropriate authority surveyor.
16. Upon completion of testing, the lifeboat should be cleared of all non-essential equipment and finally stowed in the davit as detailed in the davit Instruction/Maintenance manual.
17. Open ventilator, close all doors and hatches, leaving boat ready for emergency use.
Next:Characters of Marine Mooring Ropes With Different Materials